2nd Quarterly Report at National Grid Electricity Transmission


This report provides an overview of my experience during the second quarter of the ES Cornwall Memorial Scholarship. In November 2023, I began my placement at National Grid Electricity Transmission (NGET) in Warwick, United Kingdom in the Future Network Blueprints team. In my first quarter, I was tasked with developing Regional Strategies for the business. The development of the Regional Strategies continued during my second quarter, albeit with an increased focus on price control requirements.

The Regional Strategies are documents that enable staff to gain an understanding of the major challenges and proposed solutions within a geographic region. These documents bring together network and stakeholder requirements from across the business to provide a view of
the power system that allows staff to design the network holistically. Following an internal review in March 2024, the structure of the documents was amended to better align it with the price control submission. The Regional Strategies structure was modified to better convey the network-level context for network reinforcements and site investment decisions made in National Grid’s price control submission.

The information captured in the Regional Strategies trickled down to the Site Strategies. Site Strategies at National Grid are designed to enhance the scope of information considered in site investment decisions to ensure a consistent ‘whole system’ approach is taken. Extensive consultation with NGET personnel across the business is required to ensure the needs of all parties are accounted for. Asset health, customer connection, network reinforcement and stakeholder needs are key considerations captured by the Site Strategies.

Driven by the need to accommodate the increasing demand for new connections, connections reform is currently taking place in the United Kingdom. The connections landscape is moving towards a first ready, first connected premise allowing ready or strategically significant
projects to be accelerated, leading to faster connection times. While the change is expected to streamline the connections queue, more pressure will be put on system operators like NGET to have the flexibility to deliver accelerated projects quickly.

A full version of this report can be found here.